GATS-A03B Automatic Transfer Switch with Priority Phase, Signal Output and Adjustable V/A Protection
The GATS-A03B is a microcontroller-based automatic transfer switch that takes three lines plus neutral on the input side (N, L1, L2, L3 — AC 3×220V, 50/60Hz) and supplies a single-phase load through a 2P output (Lout + N). It comes in 63A, 80A and 100A and brings together priority phase selection, over-voltage and under-voltage protection, over-current protection with adjustable action time, automatic reconnection, and a separate signal switch output that reports the operating state to an external device. Five display windows read the three incoming line voltages (L1-in, L2-in, L3-in) plus the output voltage (L-out) and the output current (I-out), while L1/L2/L3 and Fault LEDs show which line is feeding the load and why the last operation took place. All values are entered from four front keys: over-voltage 230–300V (default 270V), under-voltage 140–220V (default 170V), over-current 1A up to the rated current, and delays from 1s to 600s. The unit mounts on a 35mm DIN rail.
Size Dimension

Working Principle
The three input lines act as candidate sources rather than three phases carried at once. The microcontroller measures L1, L2 and L3 against the stored voltage window and connects one of them to the output, which is why the 63A / 80A / 100A rating belongs to the single-phase path. Normally the load runs on the line set as priority phase (L1 by default, or Auto). If that line goes above the over-voltage setting or below the under-voltage setting, the switch releases it and moves the load to a reserve phase in less than 0.2s, so the load stays energised as long as one line remains inside the window. Trip timing is graded by the measured voltage: below 350V the unit acts within 0.1s, and above 350V within 0.02s — the faster path matters when a broken neutral pushes line voltage onto the load. A 5V hysteresis band stops the switch chattering when the voltage sits right at a threshold. When the priority phase returns and holds through the return delay (1–600s), the unit transfers back on its own, and the signal output follows the change so the event can be logged remotely.
Key Features
- Signal switch output — a dedicated terminal pair on the output side, shown in the wiring diagram as a contact separate from the power circuit, for remote indication or monitoring.
- Five display windows — three incoming line voltages plus output voltage and output current, so supply quality and load can be checked without a clamp meter.
- Priority phase selection — L1, L2, L3 or Auto, chosen in the setup menu.
- Graded trip speed — 0.1s under normal conditions, 0.02s once voltage exceeds 350V.
- Microcontroller measurement — voltage accuracy better than 1%, maximum operating phase voltage 350V.
- Adjustable timing — power-on delay 1–600s (default 5s), protection recovery delay 1–600s (default 30s).
- Over-current control — value 1A to the rated current, action time 0.1–10s, plus a continuous over-current retry count of 0–20 (OFF by default).
- Setting from four keys — M for menu and reset, ▲/▼ for digits, and a manual ON/OFF key for isolating the load.
- Service life — electrical 10⁵ operations, mechanical 10⁶ operations.
Protection Settings and Defaults
Every threshold is adjustable, and units leave the factory on the values below unless a different pre-set is agreed with the order:
- Over-voltage (oU) — range 230–300V, default 270V.
- Under-voltage (uU) — range 140–220V, default 170V.
- Over-current (oC) — range 1A up to 63A, 80A or 100A according to the model; action time (Ctt) 0.1–10s, default 0.5s.
- Continuous over-current count (CC) — 0–20, OFF by default; useful for telling a real wiring fault apart from a single starting surge.
- Trip delay — 0.1s below 350V, 0.02s above 350V, applied to both the over-voltage and the under-voltage function.
- Setting rule — the under-voltage value stays below the nominal voltage and the over-voltage value above it. On the AC 110V version keep under-voltage near 90V and over-voltage near 140V; an under-voltage figure set close to 220V would read a healthy 110V supply as too low and the load would stay off.
Installation
- Mount on a 35mm DIN rail inside a distribution board; keep to an altitude of 2000m and an ambient range of -25°C to +50°C.
- Wire N, L1, L2 and L3 to the four input terminals on the upper side; take N and Lout from the lower side to the load, following the front-panel markings.
- Connect the two signal switch terminals to the monitoring input, and confirm the contact form and rating before wiring them into a PLC, RTU or alarm panel.
- Isolate the supply before wiring and tighten the terminal screws firmly, particularly on the 80A and 100A versions.
- Power up, check that the three input windows read plausible values, then step through the setup menu to confirm oU, uU, oC, Ctt, CC, LS, Pt and rt.
- Record the final settings in the board documentation; the manual ON/OFF key isolates the load during maintenance.
Applications
Apartment blocks and multi-unit residential boards fed from a three-phase riser, shops and small offices, telecom and monitoring cabinets, pumping and irrigation control, lighting circuits, and unattended single-phase installations where the transfer or fault event needs to be reported back to a control room rather than read on the front panel.