Power Quality Solutions / New Energy Grid Integration
Power Quality Solution - New Energy

Grid-Code Power Quality for Wind, Solar & Storage

At the point of interconnection, intermittent generation and inverter harmonics stress voltage, power factor and grid-code limits. GEYA SVG / ASVG deliver dynamic reactive support from equipment rated 220V to 800V. At 10kV and 35kV metering points, high-side sampling coordinates low-side compensation to help the plant meet power-factor, voltage and flicker requirements.

The Problem

Power Quality at the Interconnection Point

Renewable plants stress the grid in three specific ways. We measure each before recommending hardware.

Reactive Power & Voltage Swings

Fast changes in PV / wind output swing the voltage at the POI and drag power factor below the level the grid operator requires.

Fix · SVG

Inverter-Sourced Harmonics

Grid-tie inverters inject current harmonics that distort the waveform, heat transformers and can fail the harmonic limits in the grid code.

Fix · AHF / ASVG

Grid-Code & LVRT Compliance

Operators demand dynamic reactive support, voltage hold and low-voltage ride-through. Heavy rooftop PV can also push feeders into over-voltage.

Fix · Dynamic SVG / AVC
Wind farm using a GEYA SVG for grid integration and reactive support
The GEYA Approach

Dynamic Reactive Support, Compliant by Design

A GY-SVG - or an all-in-one GY-ASVG - provides fast, continuous reactive power at the interconnection point, supporting voltage during generation swings and correcting power factor. Where the metering point sits on the 10kV / 35kV side, GEYA uses high-side sampling with low-side compensation, so a low-voltage unit corrects the high-side power factor to pass grid assessment.

  • GY-SVG: reactive rate ≥99%, response <10 ms, no resonance
  • High-side sampling / low-side compensation for 10kV / 35kV metering
  • GY-ASVG adds 2nd-50th harmonic + imbalance in one cabinet
  • GY-AVC regulates PV-feeder over-voltage back to 230 V
PF 0.67 → 0.95 Grid-code pass High-side measured
Proof

New-Energy Projects

When the metering point sits on the 10 kV / 35 kV side, GEYA passes grid assessment with low-voltage equipment - high-side sampling, low-side compensation. Three field-proven wiring schemes trade off accuracy, response speed and cost.

Featured project: a 309.69 kWp grid-tied rooftop PV plant in East China, metered at 400 V between the grid and the PV connection point. Power factor failed the utility assessment and the plant faced heavy penalty billing - until a 150 A TPQC installed upstream of the metering point corrected it with high-side sampling and low-side compensation.
0.67 → 0.95Average power factor
+41.8%PF improvement
≈29.5%Less line current
EndedPenalty billing
Scheme 1 wiring diagram: secondary-sampling CT and multifunction meter at the 10kV high-voltage metering point, RS-485 linked to a 380V SVG
Scheme 1 · Highest Accuracy

Multifunction Meter + Secondary-Sampling CT

A clamp-on CT taps the secondary sampling line of the 10 kV metering meter, and a multifunction meter reads its voltage and current to derive active power, reactive power and power factor. The SVG - installed on the 400 V / 800 V low-voltage side - reads these values over RS-485 and outputs exactly the reactive power needed to lift the high-side power factor to the assessment target.

  • Best for pure PV export and EV-charging stations, where load active power is small
  • Simple wiring - no need to touch the 10 kV metering secondary circuit, no outage
  • Highest compensation accuracy of the three schemes
  • Commissioning is more involved; keep meter and SVG within ~300 m (wireless link available); response up to ~3 s
High accuracyNo 10 kV outageResponse ≤3 s

Main configuration: SVG · 7-inch touchscreen · multifunction meter · secondary-sampling CT · RS-485 cable

Scheme 2 wiring diagram: CT on the 10kV high-voltage metering point feeding secondary current sampling straight into a 380V SVG
Scheme 2 · Fastest Response

Direct 10 kV High-Side CT Sampling

A dedicated CT installed on the 10 kV side feeds real-time current data straight into the SVG, which computes the high-side reactive power and power factor directly and compensates from the low-voltage side - within 10 milliseconds, the fastest of the three schemes.

  • Best for factory distributed PV - self-consumption plus surplus export, with larger load active power
  • Simple wiring and the most straightforward commissioning
  • ≤10 ms dynamic response rides through fast PV output swings
  • Needs a planned 10 kV outage to wire the CT secondary into the SVG; accuracy below Scheme 1; keep CT and SVG within ~300 m
Response ≤10 msEasy commissioningReal-time sampling

Main configuration: SVG · 7-inch touchscreen · high-side CT · secondary sampling line

Scheme 3 wiring diagram: multifunction meter, secondary CT and CSVG controller coordinating a 380V SVG with a switched capacitor bank
Scheme 3 · Best Value at Scale

Meter + CT + CSVG Hybrid Control

The same non-invasive metering as Scheme 1, plus a CSVG controller that reads the data over RS-485 and coordinates a hybrid output: the SVG handles the fast, fine-grained portion while switched capacitor banks on the 400 V side supply the bulk reactive power - high accuracy at the lowest cost per kvar.

  • Best for pure PV export and charging stations that need larger reactive capacity
  • Retrofit-friendly: reuse existing 400 V capacitor banks by adding a CSVG controller - upgrade in place, cut total cost
  • Controls up to 24 capacitor channels alongside the SVG
  • Commissioning is more involved; keep devices within ~300 m; response up to ~3 s
High accuracyLowest cost per kvar24 capacitor channels

Main configuration: SVG · CSVG controller · multifunction meter · secondary-sampling CT · RS-485 cable

Selection Guide

New Energy - Common Questions

Engineer-to-engineer answers to help you spec the right device for grid integration.

Can a low-voltage SVG correct power factor on the 10kV / 35kV side?

Yes. GEYA SVG and ASVG support high-side sampling with low-side compensation: a CT or multifunction meter samples the 10kV / 35kV side while the unit installs on the 400V / 800V side and indirectly corrects high-side power factor to meet grid assessment. Three schemes trade off accuracy, response (10 ms to about 3 s) and cost.

How does GEYA support grid-code reactive-power requirements?

A GY-SVG provides dynamic reactive support with a response under 10 ms, helping stabilize voltage during fast generation swings and correct power factor. At 10kV or 35kV metering points, high-side sampling coordinates the 400V or 800V compensation equipment. Project-level LVRT compliance must still be verified against the plant inverter, protection settings and the applicable grid code.

Rooftop PV is pushing my feeder into over-voltage - what fixes it?

Use a TPQR / GY-AVC. In a distribution area in East China, large-scale PV integration caused over-voltage and three-phase imbalance that tripped inverters; a TPQR regulated the voltage back to 230 V and rebalanced the phases to meet compliance standards.

More Solutions

Explore Other Industries

Different load, different fix. See how GEYA solves power quality across sectors.

Get Started

Connecting a Renewable Plant?

Send us your single-line diagram and grid-code requirements - our engineers will model your interconnection point and recommend the right SVG, ASVG or AVC solution.

Contact Us

Check Out The Full Catalog

Quick Info Exchange Helps Us Serve You Better
(Low-voltage and solar energy electrical components catalog)

Electrical Equipment catalog